Document emoticon standing out compared to the neetwork, folder, and messages emoticons

Cracking the Cost Performance Index (CPI)

January 13, 2024

Cost performance index (CPI) and earned value management (EVM) icons

What is the Cost Performance Index (CPI) in Project Management?

Understanding the health of your project is at the heart of effective project management. The Cost Performance Index (CPI) stands as a beacon, guiding project management decisions worldwide. Also known as earned vs. burned, the Cost Performance Index assesses the cost efficiency of a project by comparing the actual cost of work completed to the budgeted cost at a given point in time. By analyzing CPI, you gain valuable insights into resource efficiency, which enables the early identification of potential budget issues. It also aids in forecasting project costs, allowing for informed estimations throughout the project’s progress. Additionally, this metric simplifies communication about cost performance among stakeholders as it brings clarity and can be easily understood by project sponsors or customers.

Yet, interpreting its value isn’t always straightforward. Does a CPI of 0.90 always signal poor project health? Not necessarily. Let’s delve deeper into the essence of the Cost Performance Index and its pivotal role in project evaluation.

How to calculate the Cost Performance Index (CPI)?

Cost Performance Index Formula

The Cost Performance Index is calculated by dividing the Earned value (EV) by the Actual Cost (AC).

Cost Performance Index= EV/AC

A Cost Performance Index example

Let’s consider this a project with an EV of $30,000 and ACWP of $40,000 would yield a CPI of 0.75.

CPI= EV/ACWP= 30,000/40,000=0.75

Based on the Cost Performance Index calculation for this project, the project costs have exceeded the budget. Thus, to ensure the project stays within the allocated budget, immediate adjustments are necessary.

How to interpret Cost Performance Index (CPI) values?

  • CPI > 1: indicates the project is under budget and is achieving results with less than the allocated budget. The remaining budget can thus be allocated to other projects or resources.
  • CPI = 1: indicates the project is performing exactly on budget.
  • CPI < 1: Indicates the project is over the budget, suggesting that more resources are being burned than expected. Corrective actions should be taken.

A cost performance index (CPI) graph with meanings. CPI below 1 is worse than planned, CPI above 1 is better than planned, CPI of -1 is as planned.

However, interpreting Cost Performance Index values requires additional consideration of its natural fluctuations over time and of its acceptable operating range.

Why does CPI fluctuate?

The Cost Performance Index can fluctuate because of various factors.

Consider the scenario, when changes in project scope happen, such as adding extra tasks or reducing initial requirements. This will likely alter the planned vs. actual expenses, and thus have an impact on the Cost Performance Index. Likewise, delays in the project’s schedule, unforeseen weather conditions, unexpected expenses like a sudden material price increase, or a shortage of skilled labor could also cause a fluctuation in the Cost Performance Index.

Simply put, just as projects are constantly evolving due to various factors impacting their success, the CPI too remains subject to change. Thus, regularly monitoring CPI trends can help project managers foresee potential issues. For example, noticing a consistent decline in CPI might indicate underlying problems requiring attention. Thanks to a smart CPI analysis, timely, effective, and informed decisions to improve cost performance become a possibility.

Given that CPI fluctuations are to be expected during your project management processes, establishing a CPI operating range becomes essential. This range serves as a benchmark, allowing project managers to better comprehend and interpret CPI trends.

How to define the operating range?

Defining the operating range is a critical step best initiated during the project planning phase, specifically, before the project starts. Establishing this range typically begins by analyzing historical data from past projects, industry benchmarks, and expert opinions. Evaluating these factors helps in determining an acceptable range within which the metric is expected to fluctuate.

Factors like project complexity, environmental influences, and resource variability significantly impact this range. Each project establishes a unique CPI operating range, spanning from narrower ranges in controlled environments (X: 1.05 > X > 0.95) to broader spectrums in unpredictable scenarios (X: 1.50 > X > 0.5).

For instance, consider a manufacturing project located in a highly regulated facility. Given the expected minimal external disturbances and controlled environment, the project will likely operate within a narrow CPI range between 1.05 and 0.95. In contrast, a construction project in an unpredictable environment, like offshore installations, implies varying weather conditions, logistical challenges, and equipment constraints. Here, the operating range widens to accommodate these uncertainties, potentially spanning from 1.50 to 0.5.

A graph showing the cost performance index (CPI) operating range

This demonstrates how the range adapts to the unique circumstances of each project, providing a buffer for anticipated deviations and guiding project performance evaluations.

How to interpret the Cost Performance Index (CPI) in combination with the operating range?

  • CPI within the range: indicates the project’s performance aligns with expectations.
  • CPI < range: suggests potential issues like scope screep or resource inefficiencies that require a detailed review.
  • CPI > range: might highlight overestimations or missed project aspects, demanding a thorough investigation.

To conclude, projects should uphold their Cost Performance Index within the predetermined operating range, striving for a CPI of 1.00 as the benchmark. Any deviations observed should act as signals prompting a more thorough investigation into potential underlying issues.

The Cost Performance Index’s connection to Earned Value Management (CPI and EVM)

Earned Value Management (EVM) is a method used to measure project performance by integrating various project aspects, including project scope, cost, and scheduling. It uses a wide range of metrics to assess project efficiency and progress.

The Cost Performance Index plays a pivotal role in EVM, being one of the essential metrics used to evaluate a project’s cost performance. Given that CPI measures the project’s cost efficiency at specific point in time, it helps in the calculation of key EVM metrics like the Estimate At Completion (EAC).

EAC corresponds to the projected total cost of the project at the end of its life cycle based on the project’s current cost performance. It can be calculated by dividing the Budget At Completion (BAC) by the CPI. This estimation allows project managers to anticipate the project cost of completion, which provides valuable insights to project managers for decision-making throughout the project lifecycle.

Moreover, alongside CPI, the Schedule Performance Index (SPI) is another crucial component within EVM. SPI can be used to compare the actual progress of a project against the planned schedule. It reflects the project’s efficiency regarding time management and task completion. Thus, SPI contributes to the comprehensive evaluation of a project’s performance within the framework of EVM.

Get help from consulting project controls professionals

Collaborating with proficient project controls consultants goes beyond comprehending the Cost Performance Index (CPI). These experts bring multifaceted benefits to the table, from optimizing project performance metrics to implementing strategic solutions. By leveraging their expertise, your team gains access to tailored systems that efficiently capture and interpret project data. Moreover, consultants adeptly define operational ranges, decode anomalies, and provide actionable insights, steering your decisions towards enhanced project efficiency and success. Their invaluable guidance extends far beyond CPI analysis, fostering proactive approaches and ensuring sustained project excellence.

Additionally, if you are looking for advanced solutions, consider checking out Cleopatra Enterprise’s cost control and earned value management software. The tool is designed to streamline your project management processes and ensure your projects stay on track and within budget.

Conclusion

The Cost Performance Index stands as a pivotal metric in project management, offering insights into cost efficiency and aiding in predictive analysis. Understanding CPI fluctuations and aligning them within an acceptable operating range is crucial for successful project outcomes. Looking to decipher your CPI data or improve your project’s performance? Reach out today!

Get in touch via phone at +31 78 620 09 10 or drop us an email at [email protected]. Let’s discuss your CPI insights and enhance your project management strategies.

Alternatively, initiate a conversation through our contact form.

Related resources

Performing earned value management (EVM) requires professionals to have a look at schedules, time, costs, and project progress.

Scope creep, budget constraints, and aligning actual work with planned tasks are just a few of the challenges faced by project managers. Ever wondered how amid these obstacles project managers keep track of progress effectively? Earned Value Management (EVM) is their not-so-secret weapon. Understanding EVM's significance is crucial; it not…

Scope creep, budget constraints, and aligning actual work with planned tasks are just a few of the challenges…

Read blog article
Fingers going through 4 steps

What is Project Cost Management? A definition Project cost management focuses on finding the right project and carrying it out correctly. It includes activities like planning, estimating, budgeting, financing, funding, managing, controlling, and benchmarking costs to ensure timely project completion within the approved budget and enhance project performance over time.…

What is Project Cost Management? A definition Project cost management focuses on finding the right project and carrying…

Read blog article